Project Gantt Chart
Overview
This document contains the comprehensive Gantt chart for the Ohpen Data Lake Project (Q2 2026). The chart visualizes all project phases, tasks, dependencies, and key milestones.
Project Start Date: March 1, 2026
Go-Live Date: May 23, 2026
Project Duration: 3 months
Interactive Gantt Chart
Phase Breakdown
Phase 1: MVP (Weeks 1-4)
Objective: Establish foundation and core ETL pipeline
| Task | Duration | Start | End |
|---|---|---|---|
| Architecture Design | 7 days | Mar 1 | Mar 7 |
| Infrastructure Setup | 7 days | Mar 8 | Mar 14 |
| Requirements Review (Milestone) | - | Mar 14 | Mar 14 |
| ETL Development | 14 days | Mar 15 | Mar 28 |
| Infrastructure Provisioning | 7 days | Mar 22 | Mar 28 |
| CI/CD Setup | 7 days | Mar 29 | Apr 4 |
| Bronze Layer Implementation | 28 days | Mar 1 | Mar 28 |
| Silver Layer Implementation | 21 days | Mar 8 | Mar 28 |
| CloudWatch Monitoring | 14 days | Mar 15 | Mar 28 |
| ETL Complete (Milestone) | - | Mar 28 | Mar 28 |
| Schema Approval (Milestone) | - | Mar 28 | Mar 28 |
Deliverables:
- ✅ Bronze layer (raw data ingestion)
- ✅ Silver layer (validated Parquet)
- ✅ Basic ETL pipeline
- ✅ CloudWatch monitoring
Success Criteria:
- ✅ Process 1 month of historical data
- ✅ Quarantine invalid records
- ✅ Basic reporting queries work
Phase 2: Production (Weeks 5-8)
Objective: Gold layer, SQL, and production readiness
| Task | Duration | Start | End |
|---|---|---|---|
| SQL Development | 7 days | Mar 29 | Apr 4 |
| Athena Tables Setup | 7 days | Apr 5 | Apr 11 |
| SQL Testing | 7 days | Apr 12 | Apr 18 |
| Performance Validation | 7 days | Apr 19 | Apr 25 |
| Gold Layer Design (Task 2) | 7 days | Apr 12 | Apr 18 |
| SQL Aggregation Pattern (Task 3) | 7 days | Apr 19 | Apr 25 |
| Integration Testing | 7 days | Apr 19 | Apr 25 |
| Schema Versioning | 14 days | Apr 5 | Apr 18 |
| Governance Workflows | 14 days | Apr 12 | Apr 25 |
| Production Deployment | 7 days | Apr 26 | May 2 |
| UAT (Milestone) | - | Apr 25 | Apr 25 |
Deliverables:
- ✅ Gold layer structure design (Task 2) + SQL aggregation pattern (Task 3)
- ✅ Schema versioning
- ✅ Governance workflows
- ✅ Production deployment
Success Criteria:
- ✅ Automated monthly reporting
- ✅ Full audit trail
- ✅ Schema evolution process
Phase 3: Rollout (Weeks 9-12)
Objective: Testing, training, and go-live
| Task | Duration | Start | End |
|---|---|---|---|
| Production Rollout | 14 days | Apr 26 | May 9 |
| Monitoring Setup | 14 days | Apr 26 | May 9 |
| Training (Milestone) | - | May 9 | May 9 |
| Final Testing (Milestone) | - | May 16 | May 16 |
| Documentation | 7 days | May 13 | May 19 |
| Go-Live (Milestone) | - | May 23 | May 23 |
Key Activities:
- User acceptance testing
- Team training sessions
- Final validation and testing
- Production deployment
- Go-live support
Phase 4: Optimization (Month 4+)
Objective: Post-launch improvements
| Task | Duration | Start | End |
|---|---|---|---|
| Performance Tuning | 14 days | Jun 1 | Jun 14 |
| Cost Optimization | 14 days | Jun 15 | Jun 28 |
| Advanced Analytics | 14 days | Jun 15 | Jun 28 |
Deliverables:
- Performance tuning
- Cost optimization
- Advanced analytics
Key Milestones
| Milestone | Date | Week | Stakeholder Involvement |
|---|---|---|---|
| M1: Requirements Review | Mar 14, 2026 | Week 2 | All: Review & approve requirements |
| M2: ETL Complete | Mar 28, 2026 | Week 4 | Technical team validation |
| M3: Schema Approval | Mar 28, 2026 | Week 4 | Finance: Approve Gold schema Legal: Approve security |
| M4: UAT | Apr 25, 2026 | Week 8 | All: Test platform, validate reports |
| M5: Training | May 9, 2026 | Week 10 | Operations, Analysts: Attend training |
| M6: Final Testing | May 16, 2026 | Week 11 | All: Validate reports, practice processes |
| M7: Go-Live | May 23, 2026 | Week 12 | All: Support first production run |
Task Dependencies
Critical Path
- Architecture Design → Infrastructure Setup → Infrastructure Provisioning
- ETL Development → ETL Complete → Integration Testing
- SQL Development → SQL Testing → Performance Validation
- Gold Layer Design → SQL Aggregation Pattern → Integration Testing
- Integration Testing → UAT → Production Deployment → Go-Live
Parallel Workstreams
- Infrastructure & ETL: Can run in parallel after architecture design
- SQL & Gold Layer: Can run in parallel during Phase 2
- Schema Versioning & Governance: Can run in parallel during Phase 2
- Production Rollout & Monitoring: Run in parallel during Phase 3
Resource Allocation
Phase 1 (MVP)
- Data Engineers: Architecture, ETL development, infrastructure
- DevOps Engineers: CI/CD setup, infrastructure provisioning
- Data Architects: Schema design, data lake architecture
Phase 2 (Production)
- Data Engineers: SQL development, Gold layer design
- QA Engineers: Testing, performance validation
- Data Governance: Schema versioning, governance workflows
Phase 3 (Rollout)
- All Teams: UAT, training, final testing
- Operations: Production rollout, monitoring
- Documentation: Technical documentation
Phase 4 (Optimization)
- Data Engineers: Performance tuning, cost optimization
- Analytics Team: Advanced analytics
Risk Mitigation Timeline
| Risk | Mitigation | Timeline |
|---|---|---|
| Schema changes | Schema versioning process | Week 4-8 |
| Performance issues | Performance validation | Week 6 |
| Integration failures | Integration testing | Week 8 |
| User adoption | Training sessions | Week 10 |
| Production issues | Monitoring setup | Week 9-12 |
Viewing the Gantt Chart
This Gantt chart uses Mermaid syntax and can be viewed in:
- GitHub (native support)
- GitLab (native support)
- VS Code with Mermaid extension
- Online Mermaid editor: https://mermaid.live
- Documentation sites (Docusaurus, MkDocs, etc.)
Updates
Last Updated: January 2026
Project Start Date: March 1, 2026
Owner: Data Platform Team
Related Documentation
- Timeline Module - Detailed timeline information
- Project Overview - Project description
- Final Implementation Plan - Implementation details